Critical Path Method: Total Float Example

Run a forward and backward pass on a small activity-on-node network to find the project duration and the float of a non-critical activity.

A4 daysB6 daysC5 daysD3 daysE7 daysF2 daysActivity on node. Arrows show finish-to-start links with no lag.

Problem

A small site project has six activities with the durations and predecessors shown in the network (all finish-to-start, no lags). Activity A starts the project on day 0, and activity F ends it.

The total float of activity D is most nearly:

  1. 0 days
  2. 1 day
  3. 4 days
  4. 6 days

Answer

Show steps

Given

  • A: 4 days, no predecessor
  • B: 6 days, after A; C: 5 days, after A
  • D: 3 days, after B; E: 7 days, after B and C
  • F: 2 days, after D and E

Method 1, step 1: Forward and backward pass

Forward pass (left to right) gives ES and EF; E starts at max(10, 9) = 10. The project ends at days. The backward pass (right to left, starting from LF = 19) gives LS and LF; B finishes by min(14, 10) = 10.

Activityt (days)PredecessorsESEFLSLFTF
A4—04040
B6A4104100
C5A495101
D3B101314174
E7B, C101710170
F2D, E171917190

Activities with zero float (A, B, E, F) form the critical path, 19 days long.

Method 1, step 2: Total float of D

Method 2 (check): List every path

The total float of an activity equals the project duration minus the length of the longest path through that activity:

The longest path is A-B-E-F (19 days). The only path through D is A-B-D-F (15 days), so:

Both methods give the same result.

Concept

The critical path is the longest path through the network; its length is the shortest possible project duration. Total float is how long an activity can slip without delaying the project.

  • Forward pass: an activity can start only when all of its predecessors are done, so take the largest EF of the predecessors.
  • Backward pass: an activity must finish before the earliest late start of its successors, so take the smallest LS.
  • Activities on the critical path have zero total float.

See the Critical Path Method (CPM) precedence relationships (activity-on-node) under project scheduling in the Construction section of the NCEES FE Reference Handbook.

Key Formulas

Notation: = duration, ES/EF = early start/finish, LS/LF = late start/finish, TF = total float.

Common Mistakes

  • (A) 0 days: assuming D is critical because it follows a critical activity (B). Only the longest path is critical.
  • (B) 1 day: this is the float of activity C (A-C-E-F is 18 days, one day shorter than the critical path).
  • (D) 6 days: taking the late finish of D as the project end (19 − 13 = 6) and forgetting that F (2 days) still has to follow D.