Critical Path Method: Total Float Example
Run a forward and backward pass on a small activity-on-node network to find the project duration and the float of a non-critical activity.
Problem
A small site project has six activities with the durations and predecessors shown in the network (all finish-to-start, no lags). Activity A starts the project on day 0, and activity F ends it.
The total float of activity D is most nearly:
- 0 days
- 1 day
- 4 days
- 6 days
Answer
Show stepsHide steps
Given
- A: 4 days, no predecessor
- B: 6 days, after A; C: 5 days, after A
- D: 3 days, after B; E: 7 days, after B and C
- F: 2 days, after D and E
Method 1, step 1: Forward and backward pass
Forward pass (left to right) gives ES and EF; E starts at max(10, 9) = 10. The project ends at days. The backward pass (right to left, starting from LF = 19) gives LS and LF; B finishes by min(14, 10) = 10.
| Activity | t (days) | Predecessors | ES | EF | LS | LF | TF |
|---|---|---|---|---|---|---|---|
| A | 4 | — | 0 | 4 | 0 | 4 | 0 |
| B | 6 | A | 4 | 10 | 4 | 10 | 0 |
| C | 5 | A | 4 | 9 | 5 | 10 | 1 |
| D | 3 | B | 10 | 13 | 14 | 17 | 4 |
| E | 7 | B, C | 10 | 17 | 10 | 17 | 0 |
| F | 2 | D, E | 17 | 19 | 17 | 19 | 0 |
Activities with zero float (A, B, E, F) form the critical path, 19 days long.
Method 1, step 2: Total float of D
Method 2 (check): List every path
The total float of an activity equals the project duration minus the length of the longest path through that activity:
The longest path is A-B-E-F (19 days). The only path through D is A-B-D-F (15 days), so:
Both methods give the same result.
Concept
The critical path is the longest path through the network; its length is the shortest possible project duration. Total float is how long an activity can slip without delaying the project.
- Forward pass: an activity can start only when all of its predecessors are done, so take the largest EF of the predecessors.
- Backward pass: an activity must finish before the earliest late start of its successors, so take the smallest LS.
- Activities on the critical path have zero total float.
See the Critical Path Method (CPM) precedence relationships (activity-on-node) under project scheduling in the Construction section of the NCEES FE Reference Handbook.
Key Formulas
Notation: = duration, ES/EF = early start/finish, LS/LF = late start/finish, TF = total float.
Common Mistakes
- (A) 0 days: assuming D is critical because it follows a critical activity (B). Only the longest path is critical.
- (B) 1 day: this is the float of activity C (A-C-E-F is 18 days, one day shorter than the critical path).
- (D) 6 days: taking the late finish of D as the project end (19 − 13 = 6) and forgetting that F (2 days) still has to follow D.