Earned Value: Estimate at Completion Example

Turn a month-8 status report into a cost forecast: find the cost performance index, then project the final cost of the contract.

Status report at the month 8 status date
Budget at completion (BAC)$2,400,000
Planned value (PV), month 8$1,200,000
Earned value (EV), month 8$900,000
Actual cost (AC), month 8$1,000,000

Problem

A highway contract has a budget at completion of $2,400,000. At the month 8 status date, the planned value is $1,200,000, the earned value is $900,000, and the actual cost is $1,000,000. Assuming cost performance to date continues for the rest of the job, the estimate at completion is most nearly:

  1. $2,500,000
  2. $2,670,000
  3. $3,200,000
  4. $2,160,000

Answer

Show steps

Given

  • BAC = $2,400,000
  • PV = $1,200,000 (not needed for a cost forecast)
  • EV = $900,000
  • AC = $1,000,000

Step 1: Cost performance index

Each dollar spent has earned only 90 cents of planned work, so the job is over budget.

Step 2: Estimate at completion

Cost performance continues, so the remaining work is also done at a CPI of 0.90:

Most nearly $2,670,000.

Check: Estimate to complete

Both routes give the same result.

Concept

Earned value compares what was planned, what was accomplished and what it cost. CPI measures cost efficiency; SPI measures schedule efficiency. A forecast of final cost uses CPI.

  • CPI below 1 means over budget; SPI below 1 means behind schedule.
  • If today's cost efficiency continues, divide the budget by CPI.
  • The EAC equals the money already spent plus the estimate to complete.

This forecast assumes today's cost efficiency holds; if the overrun was a one-time event, BAC + (AC − EV) is the better estimate.

Related: critical path method example and the Construction Engineering topic page.

Key Formulas

Notation: = budget at completion, PV = planned value, EV = earned value, AC = actual cost, ETC = estimate to complete.

Common Mistakes

  • (A) $2,500,000: assuming the remaining work returns to budget, BAC + (AC − EV). That only holds if the overrun was a one-time event.
  • (C) $3,200,000: dividing by SPI (0.75) instead of CPI. SPI measures schedule, not cost.
  • (D) $2,160,000: multiplying BAC by CPI, which lowers the forecast on a job running over budget.
  • Swapping PV and EV when computing the indices: CPI uses EV and AC, SPI uses EV and PV.