Earned Value: Estimate at Completion Example
Turn a month-8 status report into a cost forecast: find the cost performance index, then project the final cost of the contract.
| Budget at completion (BAC) | $2,400,000 |
| Planned value (PV), month 8 | $1,200,000 |
| Earned value (EV), month 8 | $900,000 |
| Actual cost (AC), month 8 | $1,000,000 |
Problem
A highway contract has a budget at completion of $2,400,000. At the month 8 status date, the planned value is $1,200,000, the earned value is $900,000, and the actual cost is $1,000,000. Assuming cost performance to date continues for the rest of the job, the estimate at completion is most nearly:
- $2,500,000
- $2,670,000
- $3,200,000
- $2,160,000
Answer
Show stepsHide steps
Given
- BAC = $2,400,000
- PV = $1,200,000 (not needed for a cost forecast)
- EV = $900,000
- AC = $1,000,000
Step 1: Cost performance index
Each dollar spent has earned only 90 cents of planned work, so the job is over budget.
Step 2: Estimate at completion
Cost performance continues, so the remaining work is also done at a CPI of 0.90:
Most nearly $2,670,000.
Check: Estimate to complete
Both routes give the same result.
Concept
Earned value compares what was planned, what was accomplished and what it cost. CPI measures cost efficiency; SPI measures schedule efficiency. A forecast of final cost uses CPI.
- CPI below 1 means over budget; SPI below 1 means behind schedule.
- If today's cost efficiency continues, divide the budget by CPI.
- The EAC equals the money already spent plus the estimate to complete.
This forecast assumes today's cost efficiency holds; if the overrun was a one-time event, BAC + (AC − EV) is the better estimate.
Related: critical path method example and the Construction Engineering topic page.
Key Formulas
Notation: = budget at completion, PV = planned value, EV = earned value, AC = actual cost, ETC = estimate to complete.
Common Mistakes
- (A) $2,500,000: assuming the remaining work returns to budget, BAC + (AC − EV). That only holds if the overrun was a one-time event.
- (C) $3,200,000: dividing by SPI (0.75) instead of CPI. SPI measures schedule, not cost.
- (D) $2,160,000: multiplying BAC by CPI, which lowers the forecast on a job running over budget.
- Swapping PV and EV when computing the indices: CPI uses EV and AC, SPI uses EV and PV.