Identifying a Sunk Cost

Easysunk costsdecision analysis
Which item is a sunk cost when evaluating a future project decision?
  1. AFuture labor
  2. BA previously completed $20,000 study
  3. CFuture material
  4. DSalvage value
Show solution

Answer: B. A previously completed $20,000 study

The completed study is an incurred cost that cannot be changed by the present decision. Compare alternatives using future incremental costs and benefits, excluding sunk costs.