Sealing Drawings Outside Your Competence

Easysealresponsible charge
A structural PE is asked to seal electrical drawings the engineer did not prepare and is not qualified to evaluate. The engineer should:
  1. ASeal them if the project manager approves
  2. BSeal them with a disclaimer
  3. CRefuse to seal them
  4. DSeal only the cover sheet
Show solution

Answer: C. Refuse to seal them

An engineer may seal only work prepared under their responsible charge and within their competence. A disclaimer or a manager's approval does not change that.