Concrete Footing Calculator

Cubic yards and bags for spread footings, piers and strip footings

Cubic yards
0.16
Cubic meters
0.12
Cubic feet
4.2
80 lb bags
7
60 lb bags
10
40 lb bags
14

Bag yields: 0.60, 0.45 and 0.30 ft³ for 80, 60 and 40 lb premix. Waste included.

Footing Volume Formulas

  • Spread footing: V = L × W × D × number of footings
  • Round pier: V = π/4 × D² × H
  • Strip footing: V = total length × W × D

Footing size comes from the column load divided by the allowable soil bearing pressure. Volume here is only the concrete quantity. For the slab on top, use the slab calculator.

Concrete Footing FAQ

How do I calculate concrete for footings?

Multiply length × width × depth for one footing, then by the number of footings. Four 2 ft × 2 ft footings 12 in deep need 4 × 4 ft³ = 16 ft³, or 0.59 yd³.

How do I calculate concrete for a round pier or sonotube?

Use π/4 × diameter² × height. A 12 in tube 4 ft deep holds 0.785 × 1 × 4 = 3.14 ft³, about 6 bags of 80 lb premix. Pick Round column in the calculator.

What about continuous strip footings?

Treat a strip footing as one long rectangle: total length × width × depth. Add the lengths of all runs, without double-counting the corners.

How much waste should I add for footings?

Footings poured against soil often need 10 percent or more, because trench sides are uneven and the bottom is rarely flat.