Truckloads for Swelled Excavated Soil
Easyearthworkswell
1,000 m³ of bank soil swells by 25% when excavated. Trucks carry 10 m³ loose each. The number of truckloads needed is:
- A75
- B80
- C125
- D100
Show solutionHide solution
Answer: C. 125
Equation: loose volume = bank volume × (1 + swell); loads = loose volume / truck capacity. Values: bank 1,000 m³, swell 25%, truck 10 m³ loose. Step 1: loose volume = 1,000 × 1.25 = 1,250 m³. Step 2: loads = 1,250/10 = 125. 100 uses bank volume; 80 divides by the swell; 75 subtracts it.