Project Duration from Critical Path

MediumCPMcritical path
A project has two complete paths: A-B-C takes 4 + 6 + 3 days, and A-D-C takes 4 + 9 + 3 days. Assuming activities B and D can run in parallel, what is the project duration?
  1. A13 days
  2. B14 days
  3. C16 days
  4. D22 days
Show solution

Answer: C. 16 days

Path A–B–C takes 13 days and path A–D–C takes 16 days. The longest path controls completion, so the critical path is A–D–C and project duration is 16 days.
Practice this deckUntimed, one problem at a time, with your progress saved.

Related problems

Keep studying