Construction & Scheduling Practice Problems
21 problems · Construction Engineering
1 / 21
MediumCPMcritical path
A project has two complete paths: A-B-C takes 4 + 6 + 3 days, and A-D-C takes 4 + 9 + 3 days. Assuming activities B and D can run in parallel, what is the project duration?
All 21 problems
- Project Duration from Critical Path · Medium
- Total Float of a Schedule Activity · Easy
- Cost Performance Index from Earned Value · Easy
- Schedule Performance Index (SPI) · Easy
- Crew Productivity per Labor-Hour · Easy
- Total Direct Material Cost · Easy
- Trench Excavation Volume · Easy
- Actual Length from Drawing Scale · Easy
- Project Duration from an Activity Network · Medium
- Cost and Schedule Status of a Project · Medium
- Labor Cost of Placing Rebar · Medium
- Concrete Volume for Slab and Footings · Easy
- Distance Between Roadway Stations · Easy
- Pipe Slope from Invert Elevations · Easy
- Ground Distance from Plan Scale · Easy
- Purpose of a Section View on Plans · Easy
- Reading Steepness from Contour Lines · Easy
- Total Float of a CPM Activity · Easy
- CPI from Earned Value and Actual Cost · Easy
- Truckloads for Swelled Excavated Soil · Easy
- Design-Build Project Delivery Method · Easy