Construction & Scheduling Practice Problems

21 problems · Construction Engineering

1 / 21
MediumCPMcritical path
A project has two complete paths: A-B-C takes 4 + 6 + 3 days, and A-D-C takes 4 + 9 + 3 days. Assuming activities B and D can run in parallel, what is the project duration?

All 21 problems

  1. Project Duration from Critical Path · Medium
  2. Total Float of a Schedule Activity · Easy
  3. Cost Performance Index from Earned Value · Easy
  4. Schedule Performance Index (SPI) · Easy
  5. Crew Productivity per Labor-Hour · Easy
  6. Total Direct Material Cost · Easy
  7. Trench Excavation Volume · Easy
  8. Actual Length from Drawing Scale · Easy
  9. Project Duration from an Activity Network · Medium
  10. Cost and Schedule Status of a Project · Medium
  11. Labor Cost of Placing Rebar · Medium
  12. Concrete Volume for Slab and Footings · Easy
  13. Distance Between Roadway Stations · Easy
  14. Pipe Slope from Invert Elevations · Easy
  15. Ground Distance from Plan Scale · Easy
  16. Purpose of a Section View on Plans · Easy
  17. Reading Steepness from Contour Lines · Easy
  18. Total Float of a CPM Activity · Easy
  19. CPI from Earned Value and Actual Cost · Easy
  20. Truckloads for Swelled Excavated Soil · Easy
  21. Design-Build Project Delivery Method · Easy