Cost and Schedule Status of a Project
Mediumproject controlsearned value
At a progress review, a project reports a budgeted cost of work performed of $180,000, an actual cost of work performed of $210,000, and a budgeted cost of work scheduled of $200,000. The project status is best described as:
- AUnder budget and ahead of schedule
- BUnder budget and behind schedule
- COver budget and ahead of schedule
- DOver budget and behind schedule
Show solutionHide solution
Answer: D. Over budget and behind schedule
Cost variance is CV = BCWP − ACWP = 180,000 − 210,000 = −$30,000, and a negative cost variance means more was spent than the work performed was worth, so the project is over budget. Schedule variance is SV = BCWP − BCWS = 180,000 − 200,000 = −$20,000, and a negative schedule variance means less work has been completed than planned, so the project is behind schedule. Equivalently CPI = 0.86 and SPI = 0.90, both below 1.0.
Practice this deckUntimed, one problem at a time, with your progress saved.
Related problems
- Cost Performance Index from Earned Value · Construction & Scheduling
- Schedule Performance Index (SPI) · Construction & Scheduling
- CPI from Earned Value and Actual Cost · Construction & Scheduling