Cost Performance Index from Earned Value
Easyearned valueCPI
A project has earned value EV = $80,000 and actual cost AC = $100,000. What is the cost performance index (CPI)?
- A0.80
- B1.00
- C1.20
- D1.25
Show solutionHide solution
Answer: A. 0.80
CPI = EV/AC = 80,000/100,000 = 0.80. Less than 1 indicates that the earned value is below the amount spent.