Schedule Performance Index (SPI)

Easyearned valueSPI
A project has earned value EV = $90,000 and planned value PV = $100,000. What is the schedule performance index (SPI)?
  1. A0.80
  2. B0.90
  3. C1.0
  4. D1.11
Show solution

Answer: B. 0.90

SPI = EV/PV = 90,000/100,000 = 0.90. The project has earned 90% of the value planned by this point.