Crew Productivity per Labor-Hour

Easyproductivitylabor
Four workers each work 8 hours and together install 64 m2. What is their productivity in square meters per labor-hour?
  1. A0.5 m²/labor-hr
  2. B1 m²/labor-hr
  3. C2 m²/labor-hr
  4. D8 m²/labor-hr
Show solution

Answer: C. 2 m²/labor-hr

Total labor-hours = 4 × 8 = 32. Productivity = output/labor-hours = 64/32 = 2 m²/labor-hr. Using 8 hours alone would give crew-hour productivity.