Total Float of a Schedule Activity
EasyCPMfloat
An activity has early start ES = 5 days and late start LS = 8 days. What is its total float?
- A0 days
- B3 days
- C5 days
- D13 days
Show solutionHide solution
Answer: B. 3 days
Total float = LS − ES = 8 − 5 = 3 days. It is the allowable delay before the project completion date is affected, under the schedule assumptions.