Total Float of a Schedule Activity

EasyCPMfloat
An activity has early start ES = 5 days and late start LS = 8 days. What is its total float?
  1. A0 days
  2. B3 days
  3. C5 days
  4. D13 days
Show solution

Answer: B. 3 days

Total float = LS − ES = 8 − 5 = 3 days. It is the allowable delay before the project completion date is affected, under the schedule assumptions.