Total Direct Material Cost
Easyestimatingdirect cost
A project uses 500 m3 of material at $25 per m3. What is the total direct material cost?
- A$2,000
- B$10,000
- C$12,500
- D$25,000
Show solutionHide solution
Answer: C. $12,500
Direct material cost = quantity × unit price = 500 × $25 = $12,500.