How many bags of concrete you need for a slab, post holes or a known volume, in 80, 60, 50 or 40 lb bags.
Waste included, rounded up to whole bags. Water: about 6 to 9 pints per 80 lb bag (69.8 gal max for this job).
Bags needed = volume in ft³ ÷ yield per bag, rounded up. One cubic yard (27 ft³) takes 45 bags of 80 lb, 60 bags of 60 lb, 72 bags of 50 lb or 90 bags of 40 lb.
| Bag size | Yield per bag | Bags per yd³ | Water per bag |
|---|---|---|---|
| 80 lb | 0.6 ft³ (17.0 L) | 45 | 6 to 9 pt |
| 60 lb | 0.45 ft³ (12.7 L) | 60 | 4 to 7 pt |
| 50 lb | 0.375 ft³ (10.6 L) | 72 | 3.5 to 5.5 pt |
| 40 lb | 0.3 ft³ (8.5 L) | 90 | 3 to 4.5 pt |
Yields and water are from the QUIKRETE Concrete Mix (No. 1101) data sheet (revised October 2022). It also lists a 90 lb bag at 0.675 ft³ (40 per yd³) where sold. Other brands print similar yields, but use the number on your bag if it differs.
Every bag size yields about 0.0075 ft³ per pound of dry mix, which is why the table scales evenly: a yard is always about 3,600 lb of premix, whatever bag it comes in. If you need the volume of walls, columns or stairs first, use the full concrete calculator; it gives yards and bag counts for every shape.
10 × 10 × (4 ÷ 12) = 33.3 ft³ = 1.23 yd³. Bags of 80 lb: 33.3 ÷ 0.60 = 55.6, so 56 bags. The same slab takes 75 bags of 60 lb, 89 of 50 lb or 112 of 40 lb. With 10% waste it is 36.7 ft³ and 62 bags of 80 lb. At over a yard, compare the price with ready-mix. The slab calculator has a thickness chart for patios and driveways.
One hole: π/4 × (10 ÷ 12)² × 2.5 = 1.364 ft³. A 4×4 is actually 3.5 × 3.5 in, so the post takes up (3.5 ÷ 12)² × 2.5 = 0.213 ft³, leaving 1.151 ft³ of concrete per hole. Ten holes: 11.5 ft³ ÷ 0.60 = 20 bags of 80 lb (or 26 of 60 lb, 31 of 50 lb). Buying per hole would round each one up to 2 bags, also 20 here, but rounding the total is never more than per hole. Without subtracting the posts it would be 23 bags.
3 × 3 × (4 ÷ 12) = 3.0 ft³. That is 5 bags of 80 lb (3.0 ÷ 0.60 = 5.0) or 7 bags of 60 lb. Exact results like this one leave nothing for waste, so buy one spare bag.
The data sheet calls for about 6 pints of water per 80 lb bag to start, up to about 9 pints for a workable mix. Add water slowly; extra water makes the mix easier to place but lowers its strength. The calculator shows the most water the job should need, in gallons, so you can plan the hose or buckets.
Planning steel for the same pour? The rebar calculator counts bars and weight. For pier and strip footings, see the footing calculator.
45. An 80 lb bag yields about 0.60 ft³ and a cubic yard is 27 ft³, so 27 / 0.60 = 45 bags. That is 3,600 lb of dry mix.
Divide the volume in cubic feet by 0.45 and round up. A 10 × 10 ft slab 4 in thick (33.3 ft³) takes 75 bags of 60 lb; a cubic yard takes 60.
For a 10 in hole 30 in deep around a 4×4 post, about 1.15 ft³: two 80 lb bags or three 60 lb bags. Wider or deeper holes need more, so run the post-hole mode with your sizes.
They hold the same concrete per pound: every size yields about 0.0075 ft³ per lb, so 1 yd³ is 3,600 lb of mix in any size. Compare the price per bag × bags needed. Smaller bags cost more per yard but are easier to lift.
Past about 1 yd³ (45 bags of 80 lb), ready-mix is usually cheaper and gives a more uniform pour. Many suppliers charge a short-load fee for small orders, so get a quote for both.