Enter length, width and compacted thickness to get tons of hot mix asphalt for a driveway, parking lot or patch.
Includes the waste allowance. Tons are US short tons (2,000 lb). 145 lb/ft³ is FHWA's estimating weight for compacted hot mix; use your plant's job mix density for a bid.
Hot mix asphalt is sold by the ton. Find the compacted volume, then multiply by the unit weight of the mix:
The quick rule is about 110 lb of asphalt per square yard per inch of thickness (145 × 9 ÷ 12 = 108.75 lb, rounded up). Multiply by your square yards and thickness, divide by 2,000, and you have tons.
The FHWA Central Federal Lands Application Rates and Weights for Estimating Purposes lists hot asphalt mix at 2,325 kg/m³ (145.2 lb/ft³) and aggregate base at 2,225 kg/m³ (139.0 lb/ft³). The calculator uses these as presets. They are estimating values: dense-graded mixes with heavy aggregate weigh more, open-graded and porous mixes weigh less. If the plant gives you the job mix formula's compacted density, choose Custom and enter it.
| Material | lb/ft³ | kg/m³ | Tons per yd³ |
|---|---|---|---|
| Hot mix asphalt, compacted | 145 | 2,325 | 1.96 |
| Aggregate base | 139 | 2,225 | 1.88 |
Order about 11.5 tons. Check with the rule of thumb: 66.7 yd² × 3 in × 110 lb = 22,000 lb, or 11 tons before waste. These are the calculator's default inputs. Under the asphalt, a 6 in aggregate base on the same driveway is 300 ft³ × 139 ÷ 2,000 = 20.85 tons; switch the material to aggregate base and the thickness to 6 to see it.
Enter a price per tonne from your supplier and the calculator multiplies it out. It never assumes a price, because hot mix prices change with oil prices and haul distance.
How much area one US ton covers at common compacted thicknesses (145 lb/ft³):
| Thickness | ft² per ton | yd² per ton |
|---|---|---|
| 1.5 in | 110 | 12.3 |
| 2 in | 83 | 9.2 |
| 3 in | 55 | 6.1 |
| 4 in | 41 | 4.6 |
This page finds quantities; it does not design the pavement. Thickness design on the FE Civil exam is in the Highway Pavement Design section of the NCEES FE Reference Handbook, which uses the AASHTO structural number SN = a₁D₁ + a₂D₂m₂ + a₃D₃m₃ (layer coefficient × layer thickness × drainage coefficient, summed). With commonly used coefficients of 0.44 for hot mix and 0.14 for crushed stone base, and m₂ = 1.0, 3 in of asphalt over 6 in of base gives SN = 0.44 × 3 + 0.14 × 6 × 1.0 = 2.16. The required SN comes from traffic and subgrade strength. Review the topic under FE Civil transportation engineering.
Tons = length (ft) × width (ft) × thickness (in) ÷ 12 × 145 ÷ 2,000. A 50 × 12 ft driveway at 3 in compacted is 150 ft³, or about 10.9 tons of hot mix before waste.
About 1.96 tons (3,915 lb) compacted, using the FHWA estimating weight of 145 lb/ft³. Loose mix in the truck weighs less per yard, which is why asphalt is bought by the ton, not the yard.
At 145 lb/ft³ a ton covers about 9.2 yd² at 2 in thick, 6.1 yd² at 3 in and 4.6 yd² at 4 in. The shortcut is about 110 lb per square yard per inch of thickness.
Residential driveways are commonly 2 to 3 in of compacted hot mix over 4 to 8 in of compacted aggregate base. Heavier traffic or weak soil needs a thicker, designed section. These are typical values, not a design.
Compacted. The 145 lb/ft³ density is for the finished, rolled mat, so tons from compacted thickness match what the plant weighs out. Add a few percent for waste, edges and uneven base.